Telecommunications equipment placement (turnkey)
A full cycle of telecom equipment placement: from selecting a location to commissioning. We work with any type of site across the entire Republic.
Where telecom equipment can be placed
Choose a site type for detailed information
A full range of telecom equipment placement services
A complete cycle of work from site search to legalisation
Location selection and provision of space for equipment
Finding the optimal site for a base station taking into account technical requirements and the coverage area.
Negotiations with site owners
Full support throughout the approval process with owners of buildings, land plots and infrastructure.
Technical audit and site preparation
Site survey, engineering infrastructure design, preparation of the location for equipment installation.
Legal formalisation of the placement
Preparation of permit documentation, lease agreements and sanitary-epidemiological approvals.
Construction and installation works
Installation of support structures, cable routes and mounts for telecom equipment. Site preparation, installation of masts, racks and other infrastructure elements.
Electrical installation works
Arranging power supply for the equipment: laying power lines, installing distribution boards, connecting and configuring power supply systems.
Ti — technical installation
Installation and initial configuration of telecom equipment: mounting base stations, antennas and transmitting modules with subsequent functional testing.
Infrastructure for equipment placement
What site preparation includes

Space for a vandal-proof climate cabinet
Steel structure
Power connection
Cable routes
Earthing
Antenna platform
Stages of equipment placement
A transparent process from request to launch
Planning
1-2 daysDrawing up the nominal equipment placement plan and providing the coordinates of the proposed installation point for a preliminary assessment.
Site search
1-2 daysA visit to the site, inspection of the location and an assessment of the technical feasibility of the placement.
Approval of the placement point
5-7 daysPreparing and issuing technical specifications, agreeing the placement parameters and signing the contract.
Construction and electrical works
7-10 daysCarrying out construction and electrical installation works: site preparation, structure assembly and power connection.
Installation and launch
5-7 daysInstalling telecom equipment, configuring the system and commissioning the site.
Planning
1-2 daysDrawing up the nominal equipment placement plan and providing the coordinates of the proposed installation point for a preliminary assessment.
Site search
1-2 daysA visit to the site, inspection of the location and an assessment of the technical feasibility of the placement.
Approval of the placement point
5-7 daysPreparing and issuing technical specifications, agreeing the placement parameters and signing the contract.
Construction and electrical works
7-10 daysCarrying out construction and electrical installation works: site preparation, structure assembly and power connection.
Installation and launch
5-7 daysInstalling telecom equipment, configuring the system and commissioning the site.
Details on each infrastructure type

Telecom towers
Rental and placement of telecom equipment on tall structures for several operators. Best suited to backbone networks and wide coverage.

Telecom masts
Rental and placement of telecom equipment on steel structures for urban and suburban infrastructure. A reliable solution for operators.

Telecom poles
Rental and placement of telecom equipment on compact structures for dense urban areas. Fast small-cell deployment.

Rooftop sites
Rental and placement of telecom equipment on the roofs of residential and commercial buildings. Ideal for increasing network density in cities.
Along with equipment placement you can order:
End-to-end solutions for the full cycle of network deployment and maintenance
Design and construction
Turnkey construction of new AMS. From surveys to commissioning.
Monitoring and dispatching
Remote control systems and round-the-clock infrastructure monitoring.
Power supply and redundancy
Grid connection, diesel generator installation, uninterruptible power systems.
Request technical specifications
Fill in the form and our specialist will contact you within 24 hours